Non-conformities are deviations from the PAS2035 standard or project specification that emerge during retrofit work. They range from minor documentation gaps to significant quality issues. Effective management of these non-conformities is essential for maintaining project integrity, demonstrating compliance, and protecting all parties involved in the retrofit process.

What Constitutes a Non-Conformity?

A non-conformity exists when work or documentation fails to meet the requirements set out in PAS2035, the retrofit design specification, or relevant building regulations. Examples include:

Not all non-conformities carry equal weight. The framework distinguishes between major non-conformities (those affecting safety, performance or compliance) and minor ones (documentation issues or minor quality variations with limited impact).

Early Detection and Prevention

The best approach to non-conformities is prevention. This requires:

  1. Clear specifications – Ensure detailed retrofit design and site-specific specifications are agreed before work starts
  2. Competent teams – Confirm all operatives are trained and competent in PAS2035 requirements
  3. Pre-construction planning – Undertake thorough surveys and risk assessments to identify potential issues
  4. Regular site inspections – Conduct planned inspections at critical stages, not just at completion
  5. Quality assurance processes – Implement daily toolbox talks and peer checking on site

Many non-conformities emerge because communication breaks down between design, specification and installation teams. Establishing clear lines of communication and regular progress meetings reduces misunderstandings significantly.

Identifying and Recording Non-Conformities

When a non-conformity is discovered, it must be formally recorded. Documentation should include:

Key point: Create a single, centralised non-conformity register for each project. This becomes the basis for audit trails and demonstrates your compliance management to third parties.

Assign responsibility immediately. The project manager or retrofit coordinator should establish who owns resolving each non-conformity and set a clear deadline for resolution.

Resolution and Corrective Action

Non-conformities must be resolved before the project can be signed off. Resolution typically follows one of four routes:

  1. Correction – The work is redone to meet specification (most common for installation issues)
  2. Rework – The element is rebuilt or reinstalled to standard
  3. Concession – All parties agree the non-conformity is acceptable as-is, documented in writing
  4. Redesign – The specification is modified and approved by all stakeholders, with work adjusted accordingly

For each non-conformity, document the chosen resolution method and evidence that it has been implemented. Photographic records and signed-off inspection reports are essential here.

Testing and Verification

Once corrective action has been taken, verification is required. This might involve:

Only when verification confirms the non-conformity has been resolved should it be closed on the register.

Documentation and Handover

Non-conformities must never be hidden or omitted from final documentation. Your final report to the client should include:

This transparency is not a weakness—it demonstrates rigorous quality management and protects you and the client by creating an accurate record of the building's condition post-retrofit.

Learning and Continuous Improvement

Once a project is completed, review all non-conformities to identify patterns. Questions to ask include:

This analysis feeds into your continuous improvement cycle, reducing non-conformities on future projects and improving profitability by avoiding costly rework.

Managing non-conformities effectively is not about punishing mistakes—it is about maintaining standards, protecting performance, and building client confidence. A well-managed retrofit programme acknowledges that issues will arise, responds to them systematically, and closes them properly before handover.